Anchor Puncture Damage To Forecastle Store & Forepeak
Past Project – Anchor Puncture Damage To Forecastle Store & Forepeak
Scope: Cropping out and inserting of multiple puncture holes in vessel’s Stb’d side Hull, from a loose anchor during a strong storm. Staging erected externally and internally for access. On completion all welds NDT inspected and Forepeak pressure tested. All areas recoated to customer specifications.
Duration: 3 weeks